Capacity coverage: 0 of 30 records. Unknown capacity is not zero. Most community records have unverified lifecycle status. Country assignment uses generalized Natural Earth boundaries; coastal and border locations may need review.
Dated, source-backed updates. A permitting or environmental issue applies only to the scope described; it does not automatically change a facility’s lifecycle status.
Sesterce announced plans to redevelop the former Kaipola paper mill in Jämsä. Its announcement describes a 200 MW first phase and potential expansion to 600 MW, with initial works planned for 2026.
Finland’s Lupa- ja valvontavirasto calls on Tuike Finland to suspend environmentally significant preparatory work immediately, and by 23 October at the latest, until environmental impact assessments are complete. Low-impact planning, measurements and soil surveys are excluded.
Applied Digital announced an agreement providing access to up to 1 GW of potential power capacity in Finland. It plans a phased AI campus, with initial power availability anticipated from 2028.
atNorth announced plans for FIN05 on a 28.6-hectare site in Salo. The company says power is secured for a planned 75 MW first phase, with a path to as much as 230 MW across the wider development.
Tuike Finland has submitted an environmental impact assessment programme for its Vaala data-center project. The programme is open for consultation until 2 November 2026 and describes up to four server buildings around five kilometres northwest of Vaala.
Google announced €13 billion of investment in Finland over the following two years, covering infrastructure, energy and partnerships, and identified Hamina, Kajaani, Muhos and Vaala as local communities involved.