Finland · Project financing
Pure DC secures financing for Seinäjoki’s first phase
· Source checked 2026-10-12
Pure DC announced €1.3 billion of committed senior debt for the first phase of SJK01 in Seinäjoki. The company describes that phase as fully leased and planned to deliver 110 MW, with its first data hall’s substation already live.
Evidence: Primary source. No precise facility match has been established in the current map dataset.
What this means for the project
A live substation does not establish that the data center is operating. The financing is distinct from construction spending, and expansion beyond the first phase remains subject to permissions and contracting.
This is a dated account of the cited evidence. Subsequent decisions may change the position. Directory lifecycle fields retain their own evidence and verification dates.
Sources
- Pure DC ↗ · Published 2026-07-21; checked 2026-10-12